13 December 2020
Thai Hoa, Duc Hoa, Long An
6772 kWp
9684 MWh
15052
52
5478 tons
The 6,772 kWp industrial solar system was installed on 17 roofs in 10 weeks. In particular, the project achieved COD two weeks before the FIT 2 deadline on December 31, 2020.
The entire process from design, purchase, to installation completed within 12 weeks from the time the contract signation. At the same time, it still ensures safety during both construction as well as quality during long-term use.
This project located in Thai Hoa Industrial Park, Long An. Owner expect this system to produce an average of 9683 MWh and reduce about 5478 tons of CO2 per year.