TARLAC, PHILIPPINES 50 MWP

Project Highlight
Description
Commissioning

January 2016

Location

Tarlac City, Philippines

Installed Capacity

50 MWp

Annual Yield

78,070 MWh

Modules

189,432 polycrystalline

Inverters

46 SMA inverters

Mounting System

Fixed tilt, ground mount

Size of Plant

550,003 sq meters

Annual CO2 Savings

47,800 tons

PetroSolar Corporation, a company owned by PetroGreen Energy Corporation (PetroGreen) and EEI Power Corporation (EEIPC), commissioned the 50 MWp Tarlac Solar Power Project (TSPP) on January, 2016. The 50 MWp PV Power Plant’s 189,432 PV modules produce about 78,070 MWh of electricity per year, supplying some 24,000 Philippine homes and offsetting 47,800 tons of CO2 emissions annually.